The Dangote Group, a leading business conglomerate on the African continent, has reacted to reports that the commissioning date for its refinery has been set.
Several media outlets had reported that the Dangote refinery would begin operations on January 24, 2023.
However, a source within the Dangote Group has confirmed that the commissioning reports that have been shared are false.
The source noted that the reports are false and the commissioning date has not been set.
« Les informations sur la mise en service de la raffinerie Dangote par le Président Buhari le 24 janvier 2023 sont fausses et les détails seront communiqués en temps voulu. Aucune date n’a été choisie pour la mise en service du projet ».
He said
Some of the media that reported the alleged event have already deleted their posts.
In doing so, it should be noted that the Dangote refinery is 97% complete.
La Nigerian Midstream and Downstream Petroleum Regulatory Authority (NMDPRA), autrement appelée « l’Autorité », avait déjà révélé que la raffinerie était achevée à 97 %.
Farouk Ahmed, managing director of NMDPRA, revealed this development when representatives of the Dangote refinery visited him in his office recently in Abuja, FCT, to present the facility's work plan for 2022/2023.
Ahmed a également réitéré l’importance de la raffinerie Dangote pour le pays, et a assuré que « l’Autorité » apporterait tout le soutien nécessaire pour assurer l’achèvement et le démarrage des opérations dans les délais.